Current Projects

Project: Interdisciplinary Research Complex
Construction Firm: Oscar J. Boldt Construction
Start Date: November 2005

WasteCap is providing technical assistance, educational assistance, site monitoring, and backup documentation services of construction waste management efforts for this project in Madison, WI. These services will help Oscar J. Boldt Construction develop, implement, track and promote a construction waste management program whose goal is to achieve a 60 percent recycling rate.

Recycling Totals (through July 20, 2008):
Scrap Metal 254.3 tons / 508,600 lbs.
Untreated Wood 265.5 tons / 531,000 lbs.
Concrete 3,474.1 tons / 6,948,200 lbs.
Asphalt 3,626 tons / 7,252,000 lbs.
Commingled 3.5 tons / 7,000 lbs.
Cardboard 17.6 tons / 35,200 lbs.

7,640.9 tons / 15,281,800 lbs. of material recycled to date
78.02% recycling rate
$209,238.29 saved by recycling

Related Links

"Interdisciplinary Research Complex" general overview of the project.

Web Cam of the construction site and progress of the project


To achieve great recycling results on your next project, contact Susan Buchanan at (414) 961-1100 or sbuchanan@wastecapwi.org