Current Projects
Project: Johnson Controls, Glendale
Construction Firm: Hunzinger Construction
Start Date: January 2008
WasteCap Wisconsin, Inc. will provide technical assistance, educational assistance, monitor, measure, document and publicize results of
construction waste management efforts for Hunzinger Construction during the renovation of the Johnson Controls Glendale Campus during 2008,
funded by The Brico Fund. Hunzinger Construction’s goal is to achieve a 75% recycling rate.
Recycling Totals (updated April 10, 2008)
Scrap Metal 9.15 tons / 18,300 lbs.
Cardboard .56 tons / 1,120 lbs.
Reuse .08 tons / 160 lbs.
Wood 1.41 tons / 2,820 lbs.
Total Recycled to date: 11.2 tons / 22,400 lbs.
92.47% recycling rate