Current Projects - LAST UPDATED June 18, 2008
|
1212 W. Wisconsin Ave. Building at Marquette University, Milwaukee
|
|
|
NEW 153 N. Milwaukee St., Milwaukee
Contractor: LaMacchia Group
Current recycling rate: Data available soon...
|
|
|
NEW American Transmission Company, Pewaukee
Contractor: Mortenson Construction
Current recycling rate: Data available soon...
|
|
|
Aurora Medical Center, Oconomowoc
Contractor: Mortenson Construction
Current recycling rate: 62.44%
|
|
|
Columbia St. Mary's Hospital East, Milwaukee
Contractor: CG Schmidt, Barton Malow
Current recycling rate: Data available soon...%
|
|
|
Froedtert North Tower Vertical Expansion, Wauwatosa
Contractor: Mortenson Construction
Current recycling rate: 9.80%
|
|
|
Froedtert and Medical College Clinical Cancer Center, Wauwatosa
Contractor: Mortenson Construction
Architect: Zimmerman Design (local), OWP/P (Chicago)
Current recycling rate: 97.96%
Description: $70 million, 460,000 square feet
Materials being recycled: Metal, wood, concrete, cardboard
Scheduled for completion: March 2008
2007 BIG DIVERTER WINNER
|
|
|
Harley Davidson Museum, Milwaukee
Contractor: Mortenson Construction
Current recycling rate: 77.19%
|
|
|
Interdisciplinary Research Complex, Madison
Contractor: Boldt Construction
Architect: Zimmerman Design (local), HOK
Current recycling rate: 78.4%
Current savings due to recycling: $206,705.64
Description: $134 million, 420,560 square feet
Materials being recycled: Metal, wood, concrete, asphalt, commingled recyclables
Scheduled for completion: October 2008
|
|
|
Johnson Controls, Glendale
Contractor: Hunzinger Construction
Current recycling rate: 97.62%
Materials being recycled: Metal, wood, cardboard
|
|
|
Northwestern Mutual Expansion, Franklin
Contractor: Opus North Corporation
Architect: Eppstein Uhen Architects
Current recycling rate: 66.75%
Description: $85 million, 400,000 square feet
Materials being recycled: Metal, wood, concrete, cardboard, drywall
Scheduled for completion: June 2008
|
|
|
UW-Whitewater College of Business and Economics, Whitewater
Contractor: Miron Construction
Architect: Kahler Slater Architects
Current recycling rate (construction): 68%
Recycling rate (demolition): 97.6%
Description: Demolition of 3 buildings (Baker Hall 31,507 ft2, Salisbury Hall 37,115 ft2, Sayles Hall 68,378 ft2)
Materials being recycled: Cardboard, concrete, paper, metal, wood, cans and bottles
Scheduled for completion: Demolition phase completed in August 2007. Construction phase began in September 2007
2007 BIG DIVERTER WINNER
|
|
|
Veridian Homes, Madison
Contractor: Veridian Homes
Current recycling rate: 62.23%
Description: 620 homes per year
Materials being recycled: Vinyl siding, cardboard and wood
|
|
|
Wisconsin Public Service Weston 4 Power Plant, Wausau
Contractor: Washington Group International
Architect: The Boldt Company
Current recycling rate: 82.46%
Current savings due to recycling: $598,943.05
Description: $752 million, coal fired power plant addition
Materials being recycled: Scrap metal, wood, concrete, asphalt, cardboard, drywall and plastics
Scheduled for completion: April 2008
|
|
|
|
|